Town Road Projects
From Whitney Road to Penfield Town Line
Mill: May 5 – May 7 (Complete)
Pave: May 12 – May 15 (Complete)
All of Black Watch and Boxwood from Black Watch to South Ridge Trail
Gutters: June 23 – July 15 (Complete)
Mill: August 11 – August 13 (Complete)
Pave: August 25 – August 28 (Complete)
Pioneer Drive, Tall Tree Lane, Indian Trail, North Passage, Log Cabin Circle
Gutters: July 23 – August 1 (Complete)
Mill: August 14 – August 15 (Complete)
Pave: September 2 – September 3 (Complete)
2025 Chip Seal Program – Listed in order of sections of town we will be working in from first to last.
Chip Seal – July 10 – August 29 (Complete)
Fog Seal – Starting August 11th (Weather permitting) in order of sections of town below:
Section 1:
- Lanaray Park (Complete)
- Copper Beech Run (Complete)
- Tea Olive Lane (Complete)
- Nandia Pass (Complete)
- Golden Bell Court (Complete)
- Springvale Pass (Complete)
- Camellia Rise (Complete)
- Carolina Cherry Court (Complete)
- Teal Drive (Complete)
- Otterden Lane (Complete)
- Sedgmoor Lane (Complete)
- Aconbury Drive (Complete)
- Delemere Boulevard (Complete)
- Columbine Circle (Complete)
- Whitebrook Rise (Complete)
- Wheatfield Circle (Complete)
- Red Post Crescent (Complete)
- Kenicott Circle (Complete)
- Sandpiper Hill (Complete)
Section 2:
- Bent Oak Trail (Complete)
- Beatrice Cove (Complete)
- Folkside Lane (Complete)
- Shagbark Way (Complete)
- Smethwick Court (Complete)
- Lancashire Way (Complete)
- Old Stonefield Way (Complete)
- Summerfield Circle (Complete)
- Park View Drive (Complete)
- Pond View Drive (Complete)
- Wenham Lane (Complete)
- Westin Court (Complete)
- Wickersham Lane (Complete)
- Cathedral Oaks (Complete)
- Bristol View Drive (Complete)
- Spruce Ridge (Complete)
- Callaway Ridge (Complete)
- Harrington Drive (Complete)
- Lodgeview Lane (Complete)
- Sylvan Glen (Complete)
- Woodcliff Drive (Complete)
Section 3:
- Cannock Drive (Complete)
- Wedmore Road (Complete)
- Kirkby Trail (Complete)
- Chelten Rise (Complete)
- Fernly Park (Complete)
- Watchet Lane (Complete)
- Brackley Circle (Complete)
- Chardonnay Drive (Complete)
- Kenney Place (Complete)
- Courtney Drive (Complete)
Section 4: (Village)
- Williamsburg Drive (Chip Seal Complete)
- Mt Vernon Circle (Chip Seal Complete)
- Portage Circle (Chip Seal Complete)
- Amsterdam Drive (Chip Seal Complete)
- Park Circle Drive (Chip Seal Complete )
- Manor Hill Drive (Chip Seal Complete)
- Winding Brook Drive (Chip Seal Complete)
Parks:
- Spring Lake Park (Complete)
Monroe County Department of Transportation and The Town of Webster
Baird Road between Whitney Rd/Penfield Rd
Mill: August 4-8 (Complete)
Pave: August 11-13 (Complete)
Monroe County Road Projects
For information on Monroe County Roadwork in the Town of Perinton, check their website at: http://www2.monroecounty.gov/dot-construction
New York State Road Projects
For information on New York State Roadwork in the Town of Perinton, check their website at: https://www.nysdot.gov/projects.
Lane reduction along State Route 31 over I-490: NYS DOT closed the right lane for eastbound traffic along State Route 31 over Interstate 490 to accommodate bridge repair work. This lane configuration and associated work comes following a recent inspection of the bridge. The lane reduction is slated to be in place for about one month. Motorists utilizing the ramp connecting I-490 eastbound to State Route 31 eastbound will need to follow the temporary signage directing them to yield to traffic before entering State 31.